Unmanned aerial vehicle survey dates are often promised before anyone has checked whether the flight can legally and practically happen. On aerial surveys, the permissions behind a flight are separate approvals held by different people, and any one of them can move the date.

Quick Answer

Resolve three separate permissions before promising a date. Airspace: drone flights in South Africa are regulated by the South African Civil Aviation Authority under Part 101, and some areas need extra authorisation. Landowner or site occupier permission. And the site's own access and safety rules, which mines often add. None replaces another. Name who is responsible for each.

Whether a drone suits your deliverable at all is covered in our article on UAV survey or ground survey. This article is about what has to be in place before the flight.

Unmanned aerial vehicle survey: three permissions

An unmanned aerial vehicle survey sits under three separate layers of permission, and each one has a different owner and a different way of saying no.

Airspace

Remotely piloted aircraft operations in South Africa are regulated by the South African Civil Aviation Authority under Part 101 of the Civil Aviation Regulations. The rules govern where and how a drone may be flown. Some areas, such as controlled airspace or the vicinity of an aerodrome, need additional authorisation or carry restrictions. The operator is responsible for confirming the airspace classification of the specific site and any authorisation it needs.

Landowner or site occupier

Airspace authorisation is not permission to fly over a particular property. That comes from the landowner or the site occupier. On a construction site it may be the developer or the principal contractor. On a mine it is the mine. Holding one approval does not replace the other.

Site access and safety rules

A mine or industrial site often adds its own requirements on top of both: inductions, escorts, exclusion zones, blasting schedules, radio procedures and set flying windows. These belong to the site, and they apply on the day.

Permission Who holds the answer What it covers
Airspace The operator confirms it against the regulations Whether and how the aircraft may fly there
Landowner or occupier The property owner or site occupier Whether the flight may happen over that property
Site access and safety The mine or site management Inductions, exclusion zones, flying windows

Key point

Airspace, landowner and site permissions are separate. A flight needs all three, and each has its own owner.

Asked to commit to a flight date?

Send us the site location and access rules. We will list what must be resolved first.

Ask us to check the permissions

Before you promise a date

Most delayed flights trace back to one permission that was assumed rather than confirmed, so the safest approach is to confirm each one in writing before a date is agreed.

Name who confirms each item

For each permission, name one person responsible for confirming it, and record when it was confirmed. The operator confirms airspace. The client usually obtains the landowner or occupier permission. The site contact confirms access, induction and safety requirements. A date is ready to promise only when all three are confirmed.

Plan around the site's own windows

On a working mine, flying windows are set by production. Blasting, loading and vehicle movements decide when the area is safe and clear, as covered in our article on the open pit bench survey. Agree the window with operations, and agree a fallback if the window is lost. Pits on opencast mining surveys and pads on stockpile surveys are typical examples.

Allow for weather

Even with every permission in place, wind and rain can stop a flight on the day. Treat the first date as a target and agree a backup date at the same time. An unmanned aerial vehicle survey planned with a backup date rarely holds up the project that depends on it.

Keep the record with the survey

Record which permissions were held for the flight and who confirmed them. If the survey is ever questioned, the record shows it was flown with the right approvals in place. For an unmanned aerial vehicle survey repeated monthly, the same record can be reviewed and renewed each time.

Where survey cannot help you

Good planning removes most permission delays, but some decisions sit outside what any survey provider can control.

A provider cannot grant itself airspace authorisation, landowner permission or site access. It cannot change the site's safety rules or overrule a decision to stop flying on the day. And it cannot fly safely in conditions that are not suitable. Where a flight cannot go ahead, ground methods may cover part of the deliverable. Our article on drone survey cost covers how access and permissions feed into the quote.

Permissions also change. A site can add a new exclusion zone, a landowner can change, and airspace restrictions can be introduced for an event or an incident. For repeat flights, confirm each permission again before every visit rather than relying on last month's approval. A short checklist, reviewed before each flight, keeps that from being forgotten.

Key point

Confirm airspace, landowner and site permissions in writing, name who confirmed each, then promise the unmanned aerial vehicle survey date.

Need a drone survey on a mine site?

Tell us the site and its access rules. We will plan the flight and its permissions.

Get an aerial survey quote

Need ground survey where the drone cannot fly?

See how we cover areas the camera cannot reach.

See topographical surveys

Let's Build With Accuracy.

Aerial surveys planned with airspace, landowner and site permissions confirmed before the date is set.