Mine shaft survey reports often end with a reassuring line: everything checks out. On shaft sinking and equipping surveys, that line can mean very different things, because a shaft survey can deliver three separate results, and confirming one says nothing about the others.
Quick Answer
A shaft survey can deliver three results: orientation (direction), horizontal position, and vertical alignment (plumb). Each comes from a different observation. A gyro observation gives direction, not position or plumb. Ask which of the three a report covers, keep survey records at each construction milestone, and check again as the shaft deepens, because an error at the collar grows with depth.
How control is carried from surface to the shaft station is covered in our article on shaft survey control. This article is about what a shaft survey result actually confirms.
Three results in every mine shaft survey
Headgear, guides and conveyances depend on the shaft being right in three separate ways, and each one is established by a different kind of observation.
| Result | What it confirms | How it is obtained |
|---|---|---|
| Orientation | The direction underground matches surface | Orientation transfer, such as a gyro observation |
| Horizontal position | The shaft is where the plan says | Coordinate transfer down the shaft |
| Vertical alignment (plumb) | The shaft runs true from collar to bottom | Alignment observations down the shaft |
Direction is not position
A gyro observation in a shaft establishes azimuth: a direction referenced to true or grid north. It does not fix the shaft's horizontal position, and it does not confirm the shaft is plumb. Those come from separate coordinate transfer and alignment observations. Our article on what a gyro survey measures explains the gyro's role in more detail.
Ask which results the report covers
A report that says the shaft "checks out" should name which of the three it checked. If the scope was deliberately limited, for example an orientation check only, that is fine, but the report should say so, so nobody reads it as confirming position or plumb.
Why the difference matters on site
Each result affects different people. Orientation matters to the planners steering development from the shaft station. Position matters to anyone connecting the shaft to other workings or to surface infrastructure. Plumb matters to the engineers installing guides, buntons and conveyances, because a shaft that runs out of plumb changes the clearances the equipment was designed for. A mine shaft survey report that names all three, and says which were checked, lets each of those teams see at a glance whether the result they depend on has been confirmed.
Scope the survey to the stage
Not every survey needs all three results. During early sinking, position and orientation at the station may be the priority. Before equipping, plumb becomes critical. Agree the scope of each survey with the mine's survey department and the shaft contractor, and write it into the appointment.
Key point
Orientation, position and plumb are three results from three observations. Confirming one does not confirm the others.
A shaft report that leaves you unsure?
Send it to us. We will say which of the three results it confirms.
Ask us to read the reportKeeping the shaft right as it deepens
A shaft is surveyed many times during sinking and equipping, and the value of each survey depends on what was recorded at the stages before it.
Errors at the collar grow with depth
Coordinate transfer down a shaft carries forward any error present at the collar, and the effect of that error at the working level grows with the depth transferred. A check made early in the sink does not cover the levels below it. Independent checks become more important, not less, as sinking proceeds.
Record every milestone
Survey records captured at defined milestones, such as the collar, each station or inset, final depth and each equipping stage, let a later deviation be traced back to the stage where it was introduced. Without them, an investigation can only say a deviation exists, not when it began. Keep each record with its date, method and the results it covers.
Check by a different method
When a check is commissioned, it should use a different observation or method from the one that established the control, so it does not repeat the same possible error. Our article on the shaft check survey sets out what that report should state.
Recording the shaft walls
Where the shaft walls themselves need to be recorded, for example to check clearances for steelwork, 3D laser scanning can capture them with a scanner lowered down the shaft, without sending a person down.
Where survey cannot help you
A complete mine shaft survey record shows where the shaft is and how it runs, but some decisions sit outside what any survey can make.
Survey cannot set the tolerance the shaft, guides or conveyances must meet; that comes from the design. It cannot correct steelwork already installed from wrong control; it can only show how far it departs. And it cannot recover a milestone record that was never taken. The SAIMM is a useful reference for shaft sinking and mining practice in the region.
Key point
Ask every mine shaft survey report to name which of orientation, position and plumb it covers, and keep a record at every milestone.
Sinking or equipping a shaft?
Tell us the shaft and its programme. We will plan the survey at each milestone.
Get a shaft survey quoteNeed an independent shaft check?
A separate team, using a different method, can test each result.