Opencast survey handover problems rarely come from the figures themselves. On opencast mining surveys, they come from the information that should have travelled with the figures and did not, which is why the planning team keeps asking the same follow-up questions.

Quick Answer

Every opencast handover should state the survey date and extent, the coordinate reference frame and height datum, the control the survey was tied to, and the surface format and version. A deliverable can look complete and still fail to import or align in the planning software if the reference frame, format or control basis does not match what that software expects. Agree the list once with the planning team, then use it every time.

This article is specific to opencast work feeding a mine planning system. The general evidence that should arrive with any survey is covered in our survey handover checklist.

What an opencast survey handover must state

An opencast survey handover must carry seven items alongside the figures, and each one answers a question the planning team would otherwise have to ask.

Item The follow-up question it prevents
Survey date "When was this captured?"
Survey extent "Which part of the pit does this cover?"
Coordinate reference frame "Which system is this on?"
Height datum "Which heights are these?"
Control the survey was tied to "Which stations was this observed from?"
Surface format and version "Why will this not open?"
What was not captured "Is this gap empty ground or missing data?"

Date and extent travel with every figure

A volume or face-position figure is tied to the date and extent of the survey that produced it. Mining continues after the survey, so a figure used without those two facts risks being applied to ground that has since changed. Put the date and extent on the drawing, in the file name and in the covering note, so they cannot be separated from the figure.

Where the handover combines surveys captured on different days, state the date for each part. A single date on a combined surface hides the fact that some of it is older than the rest.

Reference frame, datum and control

Name the coordinate reference frame in words and by its code in the EPSG registry, state the height datum, and list the control stations used. A surface on the wrong reference will import and sit in the wrong place, which is harder to spot than a file that fails outright.

What was not captured

State any area that could not be reached or was excluded on the day. Without that note, a gap in the surface looks like empty ground, and the planning team may design over it. A short line in the handover prevents a wrong assumption that is expensive to find later.

Key point

Figures without their date, extent and reference cannot be used safely. Put those facts in the handover, not in an email that follows it.

Planning team asking the same questions each month?

Send us a recent handover. We will mark what it is missing.

Ask us to review a handover

Making the handover import first time

A handover intended for a mine planning system is only usable there if its format, reference frame and control basis match what that system expects.

Agree the format once

Ask the planning team which surface format and version their software opens, and which layer or naming conventions they use. Write that down and attach it to every survey request. Aerial and ground capture can both deliver to the same format; our article on drone survey deliverables covers the files an aerial survey should return.

Test the first delivery

Import the first handover under the new list while the surveyor is still available. Any mismatch found then is a quick fix: a format setting, a layer name or a reference code. Check that the surface lands where the previous one did, not only that the file opens. Found three months later, it can undermine every comparison made in between.

Keep the list the same across surveys

On pits with monthly measurement, the same list should apply to the pit surfaces, stockpile surveys and any volumetric work, so every surface lands in the same place in the planning model.

Keep a copy of the agreed list with the survey contract as well as with the planning team. When a surveyor changes, or a new person joins either team, the list carries the agreement forward. An opencast survey handover that follows a written list does not depend on anyone remembering what was agreed.

Key point

One agreed list, tested on the first delivery, removes most follow-up questions for every opencast survey handover after it.

Setting up regular pit surveys?

Tell us your planning software and reporting cycle. We will match the handover.

Get an opencast survey quote

Where survey cannot help you

A complete handover makes survey data usable in planning, but some decisions sit outside what any survey delivery can settle.

A survey cannot keep a figure current once mining has moved on. It cannot choose the planning software's settings, and it cannot decide whether a figure is recent enough for a particular decision. That judgement belongs to the planning team, and the date and extent on every figure are what let them make it. The survey's job is to make those facts impossible to miss. Where an older figure is about to drive a materially later decision, re-survey first. Stating the date and extent reduces the risk of using an old figure. It does not remove it.

Planning and survey models disagree?

An independent check can establish which reference each one is on.