Earthworks quantities cause disputes when two honest figures describe different things. On volumetric surveys, the survey and the contractor's payment claim are often both correct, and simply measuring different kinds of cubic metre.

Quick Answer

The same material can be reported as an in-situ (bank) volume, a loose (bulked) volume or a compacted volume, and these are different numbers. A survey usually measures in-situ volume between two surfaces. Converting it to another state needs a factor from the contract or geotechnical data, not from the survey. The contract should also state the method of measurement, because different methods are not interchangeable.

Why a single net figure can hide large movements is covered in our article on cut and fill versus net volume. This article is about the state and method behind each figure.

Three states of the same material

Soil and rock change volume as they are dug, handled and compacted, so a cubic metre in the ground, on a truck and in a finished layer are not the same quantity of material.

State Where it is measured Typical source of the figure
In-situ (bank) In the ground before excavation Survey of original and excavated surfaces
Loose (bulked) In the truck or the heap Load counts or stockpile measurement
Compacted In the finished layer Survey of layers or design template

A survey measures the geometric volume of a defined state from the surfaces captured. For an excavation, that is usually the in-situ volume: the space between the original ground and the excavated surface. A contractor counting truck loads is measuring loose material, which takes up more space than the same material did in the ground.

Where the conversion factor comes from

To convert an in-situ volume to a loose or compacted one, a factor is applied. That factor depends on the material and how it is handled, and it must come from the contract's measurement clause or from geotechnical data. The survey cannot supply it.

Key point

Before comparing two earthworks quantities, confirm that both describe the same state of the material.

A payment claim that does not match your survey?

Send us both figures and how each was produced. We will show the difference in basis.

Ask us to compare the figures

Earthworks quantities: a worked example

One example shows how a correct survey and a correct claim can disagree, and the numbers below are illustrative only, chosen to show the arithmetic, not to suggest real values.

Suppose a survey of the original ground and the excavated surface gives an in-situ volume of 10,000 cubic metres. Suppose the contract states, for this material, a factor of 1.25 from in-situ to loose. That factor is invented for this example. A real factor depends on the material and must be taken from the contract or geotechnical data.

The loose volume would then be 10,000 × 1.25 = 12,500 cubic metres. A contractor who counts loads and claims 12,500 cubic metres is not wrong, and nor is the survey. They are reporting the same material in two states. If the contract pays on in-situ volume, the payment quantity is 10,000. If it pays on loose volume, it is 12,500. The survey cannot decide which. The contract does.

Method of measurement matters too

Even within one state, the method of measurement affects the figure. Survey of layers, the average end area method and measurement against a designed template are different methods, and a volume computed by one is not directly interchangeable with one computed by another. The contract should state which method applies to payment.

The surfaces matter as well. Earthworks quantities measured against the design template can differ from those measured against the surveyed final level, because the work rarely matches the design exactly. Neither is wrong. The contract decides which one is paid, and the survey should report the one the contract names, with the other available if it is asked for.

What to agree before work starts

Most disputes over earthworks quantities are settled before they begin when four items are written into the contract and the survey brief.

State the method of measurement. State which volumetric state is paid: in-situ, loose or compacted. State which surfaces bound the calculation, such as original ground and the final excavated level. And state the source of any conversion factor. With those four agreed, the survey and the claim can be reconciled line by line. On mines, the same principle applies to opencast mining surveys and stockpile surveys. The South African Institution of Civil Engineering is a useful starting point for the contract framework most civil projects use.

Key point

Agree the method, the state, the surfaces and the factor source before work starts. Then the figures can be reconciled.

Need earthworks measured for payment?

Tell us the contract's measurement clause. We will survey to it.

Get a volumetric survey quote

Where survey cannot help you

A survey gives a defensible geometric volume, but some parts of a payment quantity sit outside what any survey can establish.

Survey cannot supply the bulking or compaction factor; that depends on the material and comes from the contract or testing. It cannot recover original ground that was never surveyed before work started, so capture it first, whether by ground survey or by aerial survey. And it cannot decide which method or state the contract pays on. That is a commercial decision for the parties.

A quantity dispute that needs an independent view?

An independent check can test each figure against its stated basis.